Mining Licenses in Armenia: Application Process, Documentation Requirements, and Timeline

Mining Licenses in Armenia: Application Process, Documentation Requirements, and Timeline

Last updated: 10 November 2026

A mining right in Armenia is granted under the Subsoil Code: an exploration permit runs up to 3 years with up to three extensions of 2 years each, and a metallic extraction permit runs 25 years with one further 25-year extension. Each right is a package of a permission, an approved programme or project, a subsoil-use contract and a mining allotment act (Art. 3(1)(5)-(8)). A foreign commercial company can hold one and can apply directly.

Registering an Armenian company gives you no right to explore or extract. That right comes only from the authorised body, after environmental expertise and, for extraction, a technical-safety opinion on the project.

At a glance

Point Rule Source
Governing law Subsoil Code of 28 November 2011; international treaties prevail where they differ Code Art. 2
Who grants the right The Ministry of Territorial Administration and Infrastructure (the authorised body) Code Arts. 3(1)(24), 17(1)(5); PM Decision 659-L, annex 11(65)
Foreign companies May hold subsoil rights and apply directly, including for metallic extraction Code Arts. 3(1)(4), 32(1), 49(1)
Exploration permit Up to 3 years, plus up to three extensions of up to 2 years each Code Arts. 27(1)(1), 42(1)
Metallic extraction 25 years, extendable once by 25 years Code Arts. 27(1)(2), 55
Non-metallic extraction Up to 20 years, extendable by up to 20 years Code Art. 27(1)(3)-(4)
Environmental expertise Category A (metallic mining): up to 80 working days EIA Law Art. 17
Beneficial-owner test, metal mining 10% or more of votes or capital Code Art. 3(1)(53)
Landowner exception Non-metallic minerals off the state balance only; no gold Code Art. 48 as amended from 1 September 2026

The Subsoil Code is the governing act for exploration and extraction (Art. 2). Armenia has no separate Mining Code in force alongside it. Other law still applies to a mining project: the Law on Environmental Impact Assessment and Expertise, the Water Code, land law and the Tax Code each add their own approvals and obligations.

A subsoil right does not need a second licence under the Law on Licensing. Article 1 of that law excludes permissions for the use of state-owned subsoil and natural resources (Law on Licensing, Art. 1). Environmental, technical, land and water approvals for the wider project are separate and still have to be obtained.

Who decides

The Code gives the power to grant subsoil rights to the “authorised body”, the state body the Government designates (Arts. 3(1)(24), 17(1)(5)). The environmental authority gives the environmental expertise opinion that the authorised body needs before it decides (Art. 51(3)-(4)). That body is the Ministry of Territorial Administration and Infrastructure: its charter, approved by Prime Minister Decision 659-L of 1 June 2019, gives it the power to grant subsoil-use rights and to consent to their change, extension, enlargement of the subsoil plot and transfer (annex, points 11(65) and 11(67)). The Ministry also publishes the official register of granted subsoil rights.

Foreign companies

A legal person, including a commercial organisation of a foreign state, may carry out geological study once it has acquired that right under the Code (Art. 32(1)), and may apply to the authorised body for a metallic extraction right (Art. 49(1)). The Code does not make an Armenian subsidiary a precondition. Branch, tax and land registrations a foreign applicant may need in practice were not established for this update.

Permit types and how long they last

The Code separates three routes. A general geological-study consent (Arts. 32-36) covers study work. A geological-study permission for extraction purposes (Arts. 37-46) is the exploration permit that leads towards mining. An extraction permission (Art. 49 onward) authorises mining itself, with separate rules for metallic and non-metallic minerals.

Permission Term Extension rules
Exploration for extraction purposes Up to 3 years Up to three successive extensions of up to 2 years each. Apply at least 6 months before expiry. After reserves are approved, one further year to prepare the extraction project if you apply within 20 days (Art. 42(1)-(2.1)).
Re-evaluation of reserves assessed 10 or more years earlier Up to 3 years No extension, except the one extra year to prepare the extraction project (Arts. 27(1)(1.1)-(1.2), 42(2.2)-(2.3)).
Metallic extraction 25 years One extension of 25 years under Art. 55. Apply at least 2 years before expiry.
Non-metallic extraction, reserves approved before 2021 Up to 20 years Extension of up to 20 years (Art. 27(1)(3)).
Non-metallic extraction, new deposits approved from 2021 20 years Extension of 20 years (Art. 27(1)(4)).

Extensions are conditional. An exploration permit is not extended if the holder has completed less than 70% of each work item in its programme, has not paid the scheduled environmental-protection fund contributions, or does not give up non-prospective areas amounting to at least half of the original allotment (Art. 42(3)-(4)). An extraction permit is not extended if less than 70% of the granted reserves has been extracted, or if the environmental-fund or monitoring payments due by the application date are unpaid (Art. 55(5.2)).

Does exploration give priority for extraction?

An exploration-right holder applying for extraction on the same site is a “privileged applicant” (Art. 3(1)(27)). Where two or more applications cover the same or overlapping areas, the privileged applicant takes priority; without one, the first registered application wins (Art. 51(10)). Priority does not convert the exploration permit into an extraction right: the extraction application still has to meet every eligibility, expertise and refusal rule.

For metallic extraction the deposit must have reserves approved by subsoil expertise within the 10 years before the application (Art. 49(1)).

What you file

Exploration permit application (Arts. 38-39)

  • State registration number of the applicant, the term requested and the minerals to be studied
  • A geological study programme meeting Art. 39 and the ministerial minimum requirements: objectives and timetable, methods and approximate volumes, geological description, geological map and a coordinate plan certified within the preceding 6 months
  • For metallic exploration, a beneficial-ownership extract from the state register current as at the preceding 5 days, replaced if a change is registered before the decision
  • Information on financial and technical capability
  • The environmental impact assessment package required by EIA Law Art. 17(2)
  • A waste-management plan with its financial guarantee, and a waste-reprocessing plan and guarantee where they apply
  • Consents of the national security, foreign affairs and defence bodies for border areas, and of the customs body inside a customs-control zone

Metallic extraction application (Art. 49(2))

  • State registration number and charter capital
  • The expected operating term, calculated from the project’s techno-economic indicators, and the list of approved minerals
  • An extraction project meeting Art. 50
  • A mine-closure programme covering dismantling, land reclamation during and after mining, social measures for the workforce, monitoring of dumps and nearby communities, an undertaking to prepare the final closure plan 2 years before the end of mining, and closure guarantees
  • A beneficial-ownership extract current as at the preceding 5 days
  • Financial and technical capability information, financial proposals and guarantees with capital and operating cost details
  • Waste-management and, where required, waste-reprocessing plans with their guarantees
  • The receipt for the state duty for environmental expertise
  • Border-area and floodplain consents where they apply

The extraction project itself (Art. 50) must cover the opening and mining systems, the reserve baseline, the whole approved balance reserves and a phased 25-year plan where needed, tailings location and construction method, infrastructure, maps and the master schedule, maximum annual output, an environmental management and monitoring plan, social impacts including resettlement, topsoil storage and land rehabilitation. Upstream construction of tailings dams is excluded, and for metallic output of up to 500,000 tonnes a year the project must address solid-tailings technology and a closed water circuit.

The statutory clock

Armenian law sets staged review periods for each authority. It does not promise an overall completion time, and the time you spend preparing the programme, project and EIA report is outside these periods.

Stage Exploration permit (Art. 40) Extraction permit (Art. 51)
Registration notice to applicant 5 days 10 days
Deficiency notice and cure Notice within 20 days; 10 days to cure Notice within 40 days; 10 days to cure. Technical-project defects: 40 days to cure
Referral for expertise Within 20 days of registration Within 40 days of registration (technical safety and environmental expertise)
Technical-safety opinion Not applicable Up to 60 days from receipt
Decision Within 10 days of a positive environmental conclusion Within 20 days of the positive opinions

Refusal grounds are a closed list. They include false information, a conflicting existing right, an excessive area, insufficient capability or guarantees, conflict with law, security or a treaty, an area where Art. 26 prohibits subsoil use, and certain earlier terminations of rights (Arts. 40(7), 51(13)). Where litigation over a terminated metallic right is pending, the decision can be suspended for up to 1 year.

Environmental expertise and public hearings

Metallic mining is category A under the EIA Law. Expertise takes up to 80 working days for category A and up to 40 for category B, extendable by up to 30 working days for additional work or information. A request for corrections suspends the clock; the revised package is due within 30 working days, or the conclusion is negative by law.

  • Community notice within 5 working days of receipt of the package
  • First public hearing between working days 21 and 25 after the notice
  • Community council decision within 30 working days after the hearing
  • Written comments: 20 working days at the initial stage; during expertise, 25 working days for category A and 20 for category B
  • Since 18 May 2026, EIA notices are published on azdarar.am

Planning an exploration or extraction application?

We review your documents with technical and environmental specialists and give you a go or no-go answer before you file.

Request a Document Review

Where subsoil use is prohibited or restricted

  • Code Art. 26: land containing graves, natural, historical or cultural monuments, or habitats and migration routes of Red Book plants and animals, in the circumstances the law sets; mercury study and mining except as a non-primary mineral; riverbed sand extraction in the border strip
  • Law on Specially Protected Nature Areas Arts. 16-19: state reserves prohibit soil-disturbing geological study, mineral extraction and ore-processing facilities; national park reserve and recreational zones carry the same bans; sanctuaries and natural monuments follow their own protection regimes
  • Law on Lake Sevan Art. 10: activity harmful to the lake ecosystem is prohibited in its central, direct and indirect impact zones, and ore-processing facilities may not be sited in the direct-impact zone
  • Water Code Art. 99(8)-(9): no work in a water area or water-protection zone except where the law provides, with further limits in groundwater-protection zones

The applicable restriction depends on the zone and its designation, so each site has to be checked against the zoning maps before an application is prepared.

Beneficial ownership for mining companies

For metal mining the Code sets a stricter test than the general register. A beneficial owner is anyone holding 10% or more of the votes or capital, directly or indirectly, or anyone who can appoint or remove a majority of management, receives a gratuitous benefit of at least 15% of the previous year’s profit, or controls the company by other means (Art. 3(1)(53)). Specified public officials and their family members are caught under the voting and benefit limbs with no minimum percentage.

Rule General register Metal mining
Threshold 20% or more (AML Law Art. 3(1)(14)) 10% or more (Code Art. 3(1)(53))
Initial declaration Within 40 days of registration A register extract current as at the preceding 5 days, with the application
Changes Within 40 days of becoming known Notify the subsoil authority within 14 days after the change is registered (Code Arts. 46(2)(2.2), 59(3)(18.2))
Annual confirmation By 20 February each year, as at 31 December Same register rule applies

Name, citizenship, the date and the basis of beneficial ownership are freely accessible in the register (Law on State Registration of Legal Entities, Art. 61(2)(7)). The EITI country page shows Armenia at “High” in its latest validation, in 2024.

The landowner exception from 1 September 2026

Law HO-317-N, in force from 1 September 2026, rewrote Art. 48. Within the boundaries of their own land, legal and natural persons may extract non-metallic minerals that are not on the state balance, without a subsoil right and without drilling or blasting, after notifying the authorised body under a Government procedure, in three cases:

  1. Non-profit use for their own economic and household needs, to a depth of 2 metres, and underground structures to 5 metres
  2. Profit-making extraction of solid non-metallic minerals of up to 20 cubic metres per calendar year
  3. Profit-making extraction of solid non-metallic minerals when building apartment blocks or public buildings, to the depth in the approved project documents

The 20 cubic metre cap applies to the second case only. The Government adopted the notification procedure by Decision 1602-N of 5 November 2026, in force from 6 November 2026, which amends Decision 152-N. The landowner notifies the authorised body in writing, giving the plot’s cadastral code, the mineral, the purpose of extraction and the volumes, and attaches a copy of the document proving ownership of the plot; in the construction case, also the relevant part of the approved project documents and a copy of the construction permit where one is required (annex, points 5-6). Within three days of registering the notice, the authorised body informs the applicant and passes the details to the Environmental Protection and Mining Inspection Body (point 7).

No small-scale gold route

The exception covers non-metallic minerals only. Armenian law has no simplified, artisanal or alluvial licence for gold or any other metal: metal extraction needs a full extraction permission under Art. 49.

Protection against later changes in rates

If the law changes, a right-holder may apply to the authorised body, within 3 years of the grant, to keep the rates in force on the grant date for the nature-use charges listed in Art. 25(1), including royalty, for resident profit tax, and for taxation of dividends, interest and royalties paid to non-residents. The protection is not automatic, covers only those charges, and does not last for the whole term of the permit.

Guarantees and payments

Guarantees are filed with the application for mine closure and for waste management and reprocessing. During operations the holder pays contributions to the environmental-protection fund for reclamation and monitoring payments for mined areas, dumps and the health and safety of neighbouring communities (Arts. 49(2), 61, 69); the exploration contract carries its own payment schedule. The Code sets no single upfront amount, and the approved guarantee templates were not reviewed for this update.

Related guides: environmental impact assessment for mining projects, land access for mining projects, mining taxation and royalty and company formation in Armenia.

Frequently asked questions

Can a foreign company apply for a mining right in Armenia?
Yes. The Subsoil Code lets a commercial organisation of a foreign state carry out geological study and apply directly for a metallic extraction right (Arts. 32(1), 49(1)). The Code does not require an Armenian subsidiary.
Do I need a licence under the Law on Licensing as well?
No. Article 1 of the Law on Licensing excludes permissions for the use of state-owned subsoil. The subsoil right comes from the Subsoil Code, and environmental, land and water approvals are obtained separately.
Can a landowner extract minerals without a permit?
Only non-metallic minerals that are not on the state balance, on the landowner’s own plot, without drilling or blasting, and after notifying the authorised body (Art. 48, from 1 September 2026). Profit-making extraction is capped at 20 cubic metres a year, except during construction of apartment or public buildings.
Is there a small-scale or alluvial gold licence?
No. The landowner exception is limited to non-metallic minerals, and every metal extraction needs a full extraction permission under Art. 49.
How long does an extraction application take?
The Code sets staged periods: registration notice in 10 days, referral for expertise within 40 days, a technical-safety opinion within 60 days and a decision within 20 days of the positive opinions. Environmental expertise for category A takes up to 80 working days, extendable by up to 30. Preparing the project and EIA report comes on top.
What beneficial-ownership threshold applies to metal mining?
10% or more of the votes or capital, directly or indirectly, plus control and benefit tests (Code Art. 3(1)(53)). The general register threshold is 20%.

Get a go or no-go answer before you invest in an application

Contact us with your site and project documents. We review them with technical and environmental specialists and respond within 1 business day.

Get a Free Consultation


Trusted by Clients from 97 Countries

4.9★ average on Google Reviews

Y. Xu

Everything was great I really appreciate the high quality service of your firm. The outcome is desirable and I am pleased. All lawyers are professional and very helpful. Thank you very much for your services. I will give 5 star for everything.

Jackson C.

My family and I would like to express our highest appreciation to Arman and the team for the responsive and professional support along the journey. Although there was an unexpected situation, Arman helped follow our cases through and provide us regular updates. Thank you.

Simon C.

All was exactly as described. Practical, cost-effective, and trustworthy legal services for all and any legal work in the Republic of Armenia. My long-term experience with this team has been good, and I am happy to recommend them for personal legal services. They respond promptly to communications, and their English/Armenian language skills are of professional standard. I will be using the services again for any issue that I have.

Get a Free Consultation
Tell us about your situation and we'll respond within 1 business day with a clear next step.

Your information is protected. We never share your details with third parties.

>